Santaldih thermal plant rated India’s most efficient

Want create site? Find Free WordPress Themes and plugins.

 Santaldih Thermal Power Station, under the West Bengal Power Development Corporation, has been rated the most efficient thermal power plant in the country in April-August 2021. During the April-July period, Santaldih had ranked third behind Korba and Sasan.
Two other state plants — CESC’s Budge Budge and WBPDCL’s Bakreshwar — are also in the top 10.
The Budge Budge plant has ranked third, up from fifth in April-July. Bakreshwar, on the other hand, has slipped two places from eighth to tenth.ncidentally, Santaldih’s rank a year ago was a dismal 31. Its plant load factor improved from 69.6% in April-August 2020 to 93% in April-August 2021. The ranking is done by the Central Electricity Authority.

Source: Times of India

Did you find apk for android? You can find new Free Android Games and apps.
Share.